Corporation Yard Improvements Project

Client: San Francisco Public Utilities Commission

As part of the Sunol Long-term improvements project, the San Francisco Public Utilities Commission developed plans to construct new facilities for the Sunol Yard and the Alameda Creek Watershed Center. WRE was retained to complete civil paving and drainage design drawings for the temporary yard.

WRE assisted with the project’s scheduling, including creating equipment usage estimates and construction schedules. WRE also completed 35%, 65%, 95% and 100% design drawings for civil drainage design and paving, prepared a Stormwater Pollution Prevention Plan, and provided engineering services during construction.